Kenora Downtown Construction this Summer

Project Start Date: early May 2008

2008 Construction Timing
• Project is expected to span approx six months from spring to fall
• Project works will be staged starting at the subway intersection
• Sewer and water works must be completed this building season

Traffic Flow
• Subway intersection will become a four way stop during construction
• Traffic will be directed onto Bernier and Matheson during construction

Main Street 2008
• Underground works on Main Street will begin mid-late June
• Main Street will be open for business throughout construction
• All businesses will be sidewalk accessible throughout construction
• The foot of Main Street will remain open for traffic and parking

Parking
• Parking will be available throughout the City, except on Main Street
• Signage will direct customers to alternate parking

Information Kiosks
• Staffed information kiosks will direct customers and visitors through the
downtown and provide information to them about the project and the community

2008 Events
• Farmer’s Market, KBI, Harbourfest and other events will be held at the
Harbourfront